GG Bridge Construction Impacts to Bicyclists & Pedestrians Posted: 2012-01-10 Southeast Side Visitor Lot Area Construction ImpactsOngoing through April/May 2012, construction of key improvements at the Southeast Visitor Area at the Golden Gate Bridge. Sidewalk Impacts - Construction and Events
Roadway Construction ImpactsWeeknight (Mondays-Fridays) lane closures start at 9:00 or 9:30 pm and end by about 4 am; up to 3 lanes are closed to accommodate the Seismic Retrofit Construction at the Marin Anchorage Housing roof and 3 lanes remain available for traffic with 1 lane south and 2 lanes north typically. These closures will continue through at least Summer 2012. Construction Projects Near the Golden Gate Bridge